Sample of Roads & Bridges Design & Supervision Works  

 

Design Review and Construction Supervision of AL FASHIR -NYALA ROAD Project (Total Length 215 Km)
Completion date: 2014
(Darfur State)

   
   
     
Description of the Project:    
Construction of 115 Km (from Km 95+000 to Km 190+000) and overlay works for 110 Km; connecting Al Fasher (South Darfur) and Nyala (North Darfur); the work included construction of (4) steel and concrete bridges.
   
     
 
 
-------    

Design Review and Construction Supervision of NYALA - ZALIGEI ROAD Project (Total Length 205 Km)
Completion Date: Oct. 2014

(North Darfur State)

   
   
     
Description of the Project:    
Overlay and rehabilitation works for 215 Km for the rod connecting Nyala, Kas and Zalingei. The project is an extension of Al Fasher Nyala road.
   
     
 
 
-------    
KARAKON - HAMASHKORAIB ROAD Project - 2012
(Kassala State)
   
     
   
     
Description of the Project:    
Construction of all-weather asphaltic road connecting Karakon and Hamashkoraib, with total length of 50 Km. The project included construction of (4) concrete and steel bridges.
   
     
 
 
-------    

Construction Supervision of EL MAIRAM - EL MOGLAD ROAD Project (Total Length 20 Km) - 2011
(South Kordofan State)

   
   
     
Description of the Project:    
Construction of the asphaltic road (20 Km), connecting El Mairam and El Moglad, from Km 167+000 to Km 187+000 (Section-2), through El Heraika and El Rogrog. The road was extension of Aweel El Mairam Road.
   
     
 
 
-------    

Design Review and Construction Supervision of ELMAIRAM - AWEEL ROAD Project.(Total Length 110 Km) - 2011
(North Kordofan State)

   
   
     
Description of the Project:    
The project entailed upgrading of existing gravel road to all-weather asphaltic road connecting El Mairam & Aweel. The total length of the road was 165 Km. The construction of the road was assigned to three contractors: (i) Danfodio (Km 0+000 to Km 55+000), (ii) Bashaier (Km 55+000 to Km 110+000) and (iii) Zadna (Km 110+000 to Km 165+000).
   
     
 
 
-------    

Construction Supervision of DEGAIN - WAGAR ROAD Project (Total Length 50 Km.) - 2011
(Kassala State)

   
   
     
Description of the Project:    
Construction of all-weather asphaltic road connecting Degain and Wagar, with total length of 50 Km. The road was an extension of Kassala - Degain road.
   
     
 
 
-------    

Construction Supervision of KASSALA - DEGAIN ROAD Project (Total Length 50 Km.) - 2009
(Kassala State)

   
   
     
Description of the Project:    
Construction of all-weather asphaltic road connecting Kassala and Degain, with total length of 50 Km. The project included construction of Karakon steel bridge across Gash River (3-spans, 180 mL).
   
     
 
 
-------    

Engineering Study and Detailed Design of KASSALA - WAGAR ROAD Project (Total Length 100 Km.) - 2004
(Kassala State)

   
   
     
Description of the Project:    
Engineering study and detailed design for the road connecting Kassala, Degain, and Wagar. The total length of the road is 100 km.
   
     
 
  ---------------  
     
  > Water and Environmental projects  